Davenport Complete Street sidewalks finished

FDOT completed sidewalk improvements on Davenport Avenue as part of a complete streets project.

The Florida Department of Transportation finished building new sidewalks along Davenport Avenue in two phases, funded through the FDOT Five-Year Work Program. The project, which ran roughly 800 meters (about half a mile), cost approximately $1.1 million and was constructed by Atlantic Civil Constructors Corp.

Work began in June 2022 and was estimated to wrap by late December 2022. The project is now marked complete in the FDOT system.

What happens next

Project is complete. No further action expected.

Timeline

Oct 27, 2021
Contract let to Atlantic Civil Constructors Corp
FDOT Work Program Contract T1816
Jun 5, 2022
Construction work began
FDOT Work Program Contract T1816
Dec 22, 2022
Estimated completion date
FDOT Work Program Contract T1816

Receipts β€” verify every claim

Every claim above links to the record it came from.

Spotted by the Lakelandmarks records pipeline Β· records checked Aug 27, 2026

Summaries are derived from public permit and agenda records and may contain errors β€” verify with the City of Lakeland or Polk County before relying on them. Spotted a mistake? Tell us and we'll fix it fast.

Sources for this page: FDOT work program.