Lakelandmarks
Built by Summit Labs β€” enterprise-grade systems, automation & technology leadership, at small‑business scale. Built by Summit Labs See what we do
Lakeland Winter Haven Auburndale Bartow Haines City Davenport Lake Wales Mulberry Polk City Fort Meade Frostproof I-4 US-27
Permitted Civic & Health
Glendale Street corridor

Lakeland builds electrical facility on Glendale Street

The City of Lakeland is constructing an electrical building and substation at 1825 Glendale Street with permits issued in October 2025.

The City of Lakeland has issued permits for a new electrical building at 1825 Glendale Street. The project includes two site generators and a substation, with permits filed in August 2024 and issued in October 2025. The work involves roofing, mechanical, electrical, and general building contractors.

The site is located along the proposed Glendale Street Trail, a planned bike path and trail corridor stretching from New Jersey Road to Lakeland Highlands Road. The trail is listed in the FDOT Five-Year Work Program for fiscal year 2026 but has not yet begun construction.

What happens next

Permits have been issued. The electrical building appears to be under or near completion, pending any remaining work on the substation roof.

Timeline

Aug 15, 2024
Permits filed for new electrical building and two site generators
Lakeland IMS BLD24-05326, BLD24-05328
Oct 14, 2025
Building and electrical permits issued
Lakeland IMS BLD24-05326, BLD24-05328
Nov 26, 2025
Roof permit for substation issued
Lakeland IMS BLD25-08909

Receipts β€” verify every claim

Spotted by the Lakelandmarks records pipeline Β· updated Jul 8, 2026

Summaries are derived from public permit and agenda records and may contain errors β€” verify with the City of Lakeland or Polk County before relying on them. Spotted a mistake? Tell us and we'll fix it fast.

Sources for this page: FDOT work program Β· City of Lakeland permit records.