Lakelandmarks Ask
Built in Lakeland by Summit Labs. See how this site is built.

Public Storage facility and 4 commercial outparcels coming to Sand Hill Road, Davenport

A public storage facility with 4 commercial outparcels is planned for Sand Hill Road in Davenport.

Under Construction Β· Latest recorded movement Dec 3, 2025

What happens next

The project is moving through final permitting and infrastructure work. Completion timeline is not yet public.

Where it is. On Sand Hill Road in Davenport.

Public Storage is developing a new facility at 2375 Sand Hill Road in Davenport. The project will include the storage building, access roads, utilities, and a stormwater pond.

The development also includes 4 commercial outparcels on the site. Fire permits for underground lines and sprinkler systems have been filed, indicating construction is underway or imminent.

Timeline

Jan 17, 2025
Dumpster enclosure permit filed
Polk County Building Permits
Jul 10, 2025
Development surety bond filed
Polk County Land Development
Nov 10, 2025
Underground fire line permit filed
Polk County Building Permits BC-2025-1376
Dec 3, 2025
Fire sprinkler system permit filed
Polk County Building Permits BC-2025-1446

Receipts β€” verify every claim

Every claim above links to the record it came from.

Edition dated Nov 27, 2026 Β· receipt snapshots show when individual records were read.

Summaries are derived from public permit and agenda records and may contain errors β€” verify with Polk County before relying on them. Spotted a mistake? Tell us and we'll fix it fast.

Sources for this page: Polk County permit records.