State Road 17 gets repaved between 5th Avenue and Crooked Lake Drive
A roughly $2.4 million resurfacing of about a mile of State Road 17.
The Florida Department of Transportation lined up a resurfacing project along State Road 17, running from 5th Avenue to Crooked Lake Drive. The stretch covers about 1,414 meters (a little under a mile) and was handled under FDOT work program item 444313.
Timothy Rose Contracting, Inc. holds the contract, valued at roughly $2,422,060. Records show the contract was let on March 27, 2024, work began on October 14, 2024, with estimated completion of September 24, 2025. The project spans fiscal years 2024 through 2026.
The FDOT records list this project's status as construction complete.